The Time Series Plot plots observations in the order of time.
1. Choose ProcessMA > Graphs > Time Series Plot.
2. In Variable, select the column containing the data.
3. In Time stamp, select the column containing the time data.
4. Click OK.
Note To select a column of data into a textbox, double-click on any of the column names shown in the list on the left of the dialog box while in the textbox.
Variable: Numeric.
Time stamp: Date/Time format.
1. Open worksheet ProcessMA > Tools > Data Files > Sample.xls.
2. Choose ProcessMA > Graphs > Time Series Plot.
3. In Variable, select F – Revenue.
4. In Time stamp, select G – Month.
5. Click OK.